Major roadway and leisure trail construction along South Sea Pines Drive from Baynard Cove to Gadwall Road in progress. Be sure to watch the March 18th video update with our Director of Capital Projects, Russell Fredericks.
- Leisure trail paving operations are in progress.
- Roadway milling operations began today, March 21st. Asphalt paving operations scheduled for next week, weather permitting.
Expect heavy traffic delays, detours and leisure trail closures. Leisure trail users are encouraged to avoid the project area during this time, as cyclists will be required to dismount and walk bikes around the work zone. Click here to view the Project Zone Map, Roadway Traffic and Leisure Trail Impact Reminders. |