SIPSD Water Pipeline Upgrade Project; Milling Scheduled to Begin 1/30 on Plantation Drive
SIPSD has provided the following project update:
- Boring and trenching are in progress in proximity to Lawton Canal. A new pipeline will be installed from the Heritage Farms area through the SPCSA Admin Building parking lot along the easement near Lake Forest in order to connect to services located at Lot 4 (Governors Road and Greenwood Drive). Expected completion time frame is 5 weeks.
- Plantation Drive, from Baynard Park Road to Lighthouse Road, Repaving Schedule:
- Asphalt milling operations will begin Monday, January 30th, weather permitting.
- SIPSD will return for roadway paving and temporary line striping the week of February 6th, weather permitting.
- Single-lane traffic closures are planned. Traffic delays are expected.
Please use caution while driving in this area and observe and obey all traffic management personnel, signage, detours, and devices. Click here to learn more about the project.