North Sea Pines Drive Infrastructure Improvement Project
Sea Pines CSA’s contractors continue conducting Major Roadway and Infrastructure Reconstruction Improvements along North Sea Pines Drive.
Ocean Gate Drainage Work
Crews successfully completed stormwater drainage pipe excavation and installation across the roadway on North Sea Pines Drive in proximity to the Ocean Gate. Crews will continue working in the Ocean Gate area next week, weather permitting.
Spotted Sandpiper Road Drainage Work
Drainage work continues on Sandpiper Road and will continue through the end of the week, weather permitting. Well-point operations on Catbird Lane will begin on Monday, December 20th.
Pictured below: Sea Pines CSA’s contractor works around utility conflicts during drainage work on Spotted Sandpiper Road.
General Project Reminders
  • North Sea Pines Drive Roadway Reconstruction will continue through January. Heavy traffic delays should be expected on North Sea Pines Drive as crews will utilize single-lane and temporary full lane closures along this roadway to accommodate the work. Traffic control will be in place, obey the speed limit within the construction zone.
  • The leisure trail along North Sea Pines Drive from The Sea Pines Beach Club to Lawton Drive is closed to bike and pedestrian traffic. Please refer to the Leisure Trail detour map here for more information.
  • The Beachwalks located at #39 & #40 are not currently accessible from North Sea Pines Drive due to this project.
  • Sea Pines CSA will continue to keep the community updated throughout this project through our community emails and our website at www.seapinesliving.com/seapinesdrive.
Sea Pines CSA Maintenance Projects Around the Community
For questions on any Sea Pines CSA Maintenance Project, please contact the Sea Pines CSA Maintenance Department by phone at 843.671.7849 or by email at csamaintenance@csaseapines.com
Leisure Trail Repairs
Backfilling edges of the leisure trails throughout the community began this week and will continue into the week of December 20th.
Roadway Asphalt Repairs
Minor asphalt repairs will continue into next week along Canvasback Road, Greenwood Drive (near Loblolly Road), Black Tern Road, Long Marsh Lane, Willow Oak West, weather permitting. Traffic control will be in place, as needed.
Lagoon Tree Trimming
Lagoon Tree Trimming is underway near Willow Oak and Willow Oak West and will continue into the week of December 20th.