Major stormwater drain pipe excavation and replacements are in progress in the areas along and across the roadway of North Sea Pines Drive between Red Cardinal Road to Spotted Sandpiper Road and the adjacent leisure trail.

HEAVY TRAFFIC EXPECTED/ UTILIZE GREENWOOD DRIVE GATE:

  • Heavy traffic delays should be expected on North Sea Pines Drive as crews will utilize single-lane closures along this roadway to accommodate the work in and along the roadway.
  • Owners, guests, and visitors are asked to plan accordingly and avoid the project area when possible by using the main gate located on Greenwood Drive. Pedestrians and cyclists are asked to seek alternate routes that avoid the project area. Please observe and obey all traffic management personnel, signage, and devices.

TEMPORARY FULL LANE CLOSURES IN PROJECT ZONE EXPECTED:

  • Short timed/temporary road closures in both directions along North Sea Pines Drive between Red Cardinal Road to Spotted Sandpiper Road will continue through next week as the main stormwater drainage pipes that cross this major roadway are removed and replaced.

ADDITIONAL PROJECT REMINDERS:

  • The leisure trail along North Sea Pines Drive from The Sea Pines Beach Club to Lawton Drive is closed to bike and pedestrian traffic. Please refer to the Leisure Trail detour map here for more information.
  • The Beachwalks located at #39 & #40 are not currently accessible from North Sea Pines Drive due to this project.

Catbird Lane & Spotted Sandpiper Road Drainage Work to begin November 29th

Sea Pines CSA’s contractor will begin well point operations the week of November 29th to remove groundwater before excavation.
  • Well point pumps and equipment will be set up in the roadway.
  • Work is expected to take 2 weeks, weather permitting.
Sea Pines CSA will continue to keep the community updated throughout this project through our community emails and our website at www.seapinesliving.com/seapinesdrive.

Road Drainage Work to Begin Near the Ocean Gate the Week of December 6th

Construction crews will conduct major infrastructure improvement work near the Ocean Gate in Sea Pines the week of December 6th. This portion of the work occurring in the inbound lane is expected to take approximately 3 days to complete, weather permitting.

Due to limitations on working space and the need to excavate stormwater drainage pipe and install replacement pipe, the inbound lane of traffic at the Ocean Gate (Cordillo Pkwy. At South Forest Beach Drive) will be closed from 7:00 am to 5:00 pm during the work.

Drivers coming inbound into Sea Pines will need to use the Greenwood Gate located off of the Sea Pines Circle during the stated timeframe. Traffic control and flaggers will be present during this work, drivers are asked to use caution in the work zone. Leisure trails in this area of North Sea Pines Drive and the Ocean Gate will be closed in both directions to accommodate this work.

Sea Pines CSA will continue to keep you updated and will provide additional details and firm dates on this planned work and lane closures as we near the week of December 6th.