This week our contractor successfully installed approximately 1,350 tons of asphalt during overnight roadway resurfacing operations on Greenwood Drive (from Sea Pines Circle to Club Course Drive).

Crews milling the old roadway along the project zone.

Crews installing new asphalt along the project zone.

Utilizing an asphalt roller, the new asphalt pavement surface is compacted and smoothed

What’s Next:

Our contractor will conduct clean-up operations along the project zone and will return after the necessary curing period to complete crosswalk stamping, permanent line striping, and install roadway reflectors.