Sea Pines CSA Maintenance Projects (4/28/22-5/5/22)

Stormwater Maintenance
Line Jetting on Governors Road and Wood Duck Road will begin the week of May 2nd, weather permitting. This process cleans sediment from drainage pipes to improve flow.
Tree Care Management
Roadway tree trimming to remove dead or hazardous branches over Gull Point Road will begin the week of May 2nd, weather permitting.
Stormwater Repair
Drainage pipe cleaning
at the lagoon near Tupelo Road and Lawton Drive will begin the week of May 2nd, weather permitting. This work will help improve the lagoon flow in this area.
Club Course Area Ditch Cleaning
This week Sea Pines CSA’s contractor began ditch and pipe cleanout work around Pine Island Road and Governors Road. Work is estimated to take approximately 2 weeks, weather permitting.
Pictured: Sea Pines CSA’s contractor preparing to conduct work on Pine Island Road.