Roadway Milling Operations in Progress on North Sea Pines Drive

  • Weather permitting, roadway milling operations will be completed by the end of this week on North Sea Pines Drive.
  • Due to the nature of this work, heavy traffic delays are expected.
  • Flag persons will be present as needed to control traffic with alternating single-lane closures in the designated work zone.
  • Please use caution while driving in this area and observe the work zone speed limit of 15 mph and obey all traffic management personnel, signage and devices.
  • Leisure trails remain closed in the project zone. Please refer to the Leisure Trail detour map here for more information.
  • To avoid delays in the project area, please use the main gate located on Greenwood Drive.

What’s Next:

  • Major milling operations will be followed by roadway alignment/widening work, temporary line stripping, and then roadway paving. Crews will also apply temporary line stripping to the paved roadway and then return after the necessary curing period to complete permanent line stripping, crosswalk stamping and install roadway reflectors.
  • Following paving operations on North Sea Pines Drive, milling and paving operations will be scheduled for the following roads: Catbird Lane, Sandhill Crane Road, Mockingbird Lane, Pyxie Lane, and a section of Lawton Drive from North Sea Pines Drive to Night Heron Lane.

How to Stay Updated:

For full project details, please visit our website at www.seapinesliving.com/seapinesdrive.