December 1, 2021
North Sea Pines Drive Phase 2 Roadway Reconstruction Project Update:
Sea Pines Ocean Gate Lane Closures Scheduled for the Week of December 6, 2021
Due to limitations on working space and the need to excavate stormwater drainage pipe and install replacement pipe, periodic road closures at the Ocean Gate (located at Cordillo Parkway and South Forest Beach Drive) will be utilized during the week of December 6, 2021.
Inbound Lane Closure Information
- The Inbound Lane at the Ocean Gate will be CLOSED to traffic from 7 AM – 5 PM, Monday, December 6th through Wednesday, December 8th, weather permitting.
- Drivers arrving inbound into Sea Pines must use the Greenwood Gate located off of the Sea Pines Circle during the stated timeframe.
Tentative Outbound Lane Closure Information
- The Outbound Lane closure at the Ocean Gate is tentatively scheduled for 7 AM- 5 PM, Thursday, December 9th through Saturday, December 11th, weather permitting
- Drivers exiting Sea Pines must use the Greenwood Gate located off of Greenwood Drive.
- Sea Pines CSA will confirm dates on the outbound lane closures as they are provided by our contractor.
Additional Project Reminders:
- Traffic control and flaggers will be present during this work, drivers are asked to use caution in the work zone.
- Leisure trails near the Ocean Gate will be closed in both directions to accommodate this work.
- Emergency vehicles will have continuous access during these closures.
- Heavy traffic delays are expected, please plan accordingly.
How to Stay Updated
- Sea Pines CSA will continue to keep the community updated throughout this project through our community emails and our website at www.seapinesliving.com/seapinesdrive.